Courtesy : India today

Bullet train 

With only 17% of the work of the Centre’s ambitious Bullet Train project completed so far, the completion is likely to miss its 2023 deadline. The data shared by the National High-Speed Rail Corporation Limited (NHSRCL) in response to a Right to Information (RTI) query filed by India Today cited several reasons, such as Covid, land acquisition issues, etc, for the delay.

17% WORK DONE SO FAR

Responding to our query on how much work had been completed so far, National High-Speed Rail Corporation Limited (NHSRCL) said, “Approximately 17% work of Mumbai-Ahmedabad high-speed rail project had been completed till Feb 1, 2022.”

ALSO READ | 89% of land needed for bullet train project acquired: Railway Minister tells Lok Sabha

NHSRCL, the nodal body responsible for the execution of the bullet train project, attributed the hold-up to Covid, delay in land acquisition in Maharashtra and award of the tenders. In response to our RTI query, it said, “As per a joint feasibility report, the Mumbai-Ahmedabad high-speed rail project is targeted for completion by 2023. However, the timeline for the commissioning of the project can be fixed after the assessment of the impact of reasons for the delay.”

COMMISSIONING DATE TO BE REASSESSED

Responding to the question pertaining to the total land acquired, it said, “Out of the total land requirement of approximately 1,396 hectares, about 1,196 hectares have been acquired.” This means that the bullet train project has acquired around 86% of the required land and needs to acquire around 200 hectares of land now.

With only 17% of the work of the Centre’s ambitious Bullet Train project completed so far, the completion is likely to miss its 2023 deadline. The data shared by the National High-Speed Rail Corporation Limited (NHSRCL) in response to a Right to Information (RTI) query filed by India Today cited several reasons, such as Covid, land acquisition issues, etc, for the delay.

17% WORK DONE SO FAR

Responding to our query on how much work had been completed so far, National High-Speed Rail Corporation Limited (NHSRCL) said, “Approximately 17% work of Mumbai-Ahmedabad high-speed rail project had been completed till Feb 1, 2022.”

ALSO READ | 89% of land needed for bullet train project acquired: Railway Minister tells Lok Sabha

NHSRCL, the nodal body responsible for the execution of the bullet train project, attributed the hold-up to Covid, delay in land acquisition in Maharashtra and award of the tenders. In response to our RTI query, it said, “As per a joint feasibility report, the Mumbai-Ahmedabad high-speed rail project is targeted for completion by 2023. However, the timeline for the commissioning of the project can be fixed after the assessment of the impact of reasons for the delay.”

COMMISSIONING DATE TO BE REASSESSED

Responding to the question pertaining to the total land acquired, it said, “Out of the total land requirement of approximately 1,396 hectares, about 1,196 hectares have been acquired.” This means that the bullet train project has acquired around 86% of the required land and needs to acquire around 200 hectares of land now.

Explore More

Permaculture

COURTESY  :  www.permaculture.co.uk PErmaculture Permaculture is an innovative framework for creating sustainable ways of living. It is a practical method of developing ecologically harmonious, efficient and productive systems that can

energy management

Courtesy : n-trak Energy management What Is Energy Management & How Can You Use It? This article explains what energy management is, why it is important today, and how you can use

Green interior

Green interior Courtesy : www.freepressjournal.in The interior design of retail space can significantly impact the sales of retail stores and other commercial areas. To increase profits, many stores are beginning